Tuesday 28 January 2020

PMI PMP Question Answer

If you are writing a proposal for additional funding, which communication style should you choose?

A. formal and horizontal
B. formal and vertical
C. informal and vertical
D. informal and horizontal

Answer: B


If you want a group of experts to identify project risks, but also want unbiased data, what is an appropriate technique to use?

A. Interviewing
B. Delphi technique
C. Assumption analysis
D. Brainstorming

Answer: B


Sunday 29 September 2019

PMI PMP Question Answer

A RACI chart is an example of a _________________.

A. Network
B. Flowchart
C. Responsibility assignment matrix
D. Hierarchical-type organization chart

Answer: C


Your company has temporarily assigned you to serve as a project manager at a company location outside your home country. While meeting with a vendor your first day on the job, you are presented with a gift. The corporate policy at the headquarters in your home country prohibits employees from accepting these types of gifts. However, as you are new to this location, you believe- but are not sure-that the local policy, as well as local custom may differ. How should you respond?

A. Provide a gift of similar value to the vendor at your next meeting.
B. Accept the gift but do not tell anyone.
C. Respectfully tell the vendor you are not sure of corporate policy, and will need to ask your management before you can accept gifts of any size.
D. Accept the gift this time, but ask your manager about the local policy afterwards.

Answer: C

Monday 14 January 2019

PMI PMP Question Answer

During the Plan Procurement Management phase, the make-or-____analysis must be completed. This technique prompts the project team to determine the source of their item.

A. lease
B. buy
C. find
D. ignore

Answer: B



Which of these precedence relationships is least commonly used in Precedence Diagramming Method?


A. Start to Start
B. Finish to Finish
C. Finish to Start
D. Start to Finish

Answer: D

Sunday 23 September 2018

PMI PMP Question Answer

Which of the following is a tool or technique used in the Monitor and Control Project Work process?

A. Expert judgment
B. Rejected change requests
C. Earned value technique
D. Change control tools

Answer: A


A large network hardware upgrade project was scheduled to take place over a weekend. During the course of the implementation, several previously unidentified dependencies for additional materials were discovered. The project manager gave approval for the tech staff doing the implementation procure with corporate credit cards several hundred dollars worth of additional equipment required to complete the implementation. However these additional expenses caused the project to exceed its budget. How should the project manager handle this?

A. Ask the IT Director to cover those expenses from his budget.
B. Advise the staff to submit expense reports for the purchases. Because the cost is relatively small, it can be categorized as miscellaneous purchases that are not associated with the project.
C. Notify the project stakeholders immediately of the additional expenses incurred and follow project and or company procedures for budget variances.
D. Do nothing- that's what reserves are for.

Answer: C

Wednesday 21 February 2018

PMP Launches Charity Partnership To Help Victims Of Modern Slavery


PMP Recruitment, part of the Cordant Group, has launched a partnership with the charity organization Unseen that will help raise vital funds and supplies for the victims of modern slavery.

The recruitment specialist will promote a fundraising event every month during 2018, while offering support to victims who may be seeking employment opportunities while seeking to rebuild their lives.

PMP will work with the Cordant Group's portfolio of expert brands to provide free support to Unseen's internal recruitment campaigns, which include functions such as safe home managers, support workers and communications officers.

In addition, the recruitment specialist will help help survivors of modern slavery to return to independent living through support in occupational health, return to work schemes, learning and flexible placement at work.

Jamie Reynolds, CEO of PMP, said: "Unseen offers a fantastic job, and we will seek to offer support and raise vital funds that will be used to help many poor people who have been victims of modern slavery practices."

In September 2017, Cordant Group announced that it would become the largest social enterprise in the United Kingdom, reinvesting all its profits in initiatives and programs designed to improve lives and society.

Wednesday 20 December 2017

PMI PMP Question Answer

The most detailed level of the WBS is called the _______________ .

A. WBS element
B. Work package
C. Project scope
D. Deliverable

Answer: B


Which of the following is a hierarchical representation of project risks?


A. Risk Register
B. Risk Mitigation
C. Risk categories
D. Risk Breakdown Structure

Answer: D

Monday 6 November 2017

PMI PMP Question Answer

If you are requesting a vendor quote for a defined scope, what is the recommended contract type?

A. Fixed price
B. Commission
C. Cost reimbursable
D. Time and materials

Answer: A


All of the following are interpersonal skills EXCEPT:


A. Resisting to change
B. Building trust
C. Resolving conflict
D. Active listening

Answer: A