A project manager in a predominantly hierarchical organization has been assigned a major project with aggressive timelines. 
The BEST approach for developing an initial project charter in this environment is to:

A. Create a project charter using brainstorming sessions with potential team members and stakeholders..
B. Create and present a draft project charter to potential team members and stakeholders to solicit their input.
C. Create a project charter jointly with management for distribution to potential team members and stakeholders.
D. Create a project charter with the functional managers and present it to the sponsor for signature.

Answer: C