Tuesday 1 March 2016

Pass4sure PMP Question Answer

Daniel is managing the development of an ecommerce website for his organization. Daniel enjoys coercive powers and has assigned Julie, a project team member, to facilitate the team meetings. During any team meeting, Julie must?

A. Influence team members to support the project manager's decisions
B. Support the team members to challenge the project manager's decisions
C. Negotiate with team members to achieve the project objectives
D. Remain neutral and facilitate the meetings

Answer: D


You are a consulting project manager and have been contracted by an investment bank to run a large information technology project that is expected to last 15
months. During the Direct and Manage Project Work process, you discover that several regulatory requirements have not been addressed in the project
management plan. Failure to meet these requirements could result in legal action against the company. However, implementing the technology to comply with
these regulations exceeds the budget and scope of the project, and could result in the cancellation of the project. What should you do?


A. Submit a change request to incorporate the missed requirements to the project's scope.
B. Do not do anything as these requirements are not a part of the scope baseline.
C. Request additional funds to implement these requirements.
D. This is a classical example of scope creep and such requirements must be ignored.

Answer: A

No comments:

Post a Comment