Tuesday 18 April 2017

PMI PMP Question Answer

Which of the following is not an organizational process asset that is used during the Plan Human Resource Management process?

A. Template for organizational charts
B. Template for position descriptions
C. Standardized role descriptions
D. Standardized stakeholder list

Answer: D


Perform Integrated Change Control includes several configuration management activities. Which of the following is not part of Perform Integrated Change Control?

A. Change request
B. Configuration Verification
C. Configuration Status Accounting
D. Configuration Identification

Answer: A

1 comment:

  1. My first and foremost step was to pick a reliable study material and I downloaded PMP braindumps from Dumps4download. A beautiful description of all the topics was packed in this study guide. PMP Dumps material helped me solve all the questions in the final.

    ReplyDelete